What an ADU costs in San Jose

Two numbers, kept apart. City fees come from the city's own fee pages. The build price is our estimate from the last owner survey and today's published prices. How we got it

Official City fees

$13,092

Detached ADU up to 750 sq ft; $22,312 for 751 to 1,200 sq ft. Average of recent permits. [1][2]

Our estimate Building it

$350k–465k

750 sq ft detached, design and construction. Middle of the range: $405k.[3][4][5][6]

All in, before school and utility fees: about $363k to $478k for a 750 sq ft detached ADU. Adjust it for your lot

18 licensed builders list San Jose on their own sites. Your quote request goes to the Bay Area ADU Builders team.

Get 3 quotes

Estimate your ADU

Change the type and size. City fees come from San Jose's own averages; the building cost is our estimate.

Type
School districts
Building it (our estimate)
—
City permit fees (city average)
—
School fees (rate × the whole ADU once it's over 500 sq ft, capped at $5.38)
—
Likely total
—

Building (middle) City fees School fees

Not included: water and sewer connection, and site surprises like a long utility run or a crane. See the fee list below.

Get 3 quotes to check this number

Licensed builders who list San Jose

All 18

The top three by our public score for San Jose. Some publish prices, which is the quickest check on the estimate above.

Every fee San Jose can charge

Building permit, plan review and inspection (fee schedule) $3,323 up to 750 sq ft; $5,151 for 751 to 1,200 sq ft[7] Modular units pay 10% less for plan review and 20% less for inspection.
Construction taxes 3.96% of valuation, plus $330 per unit[7] Valuation uses $169.09 per sq ft.
Parkland fee $0 under 750 sq ft; $1,700 to $8,900 at 750 sq ft and up, by zone[8][9]
School fees $1.36 to $5.38 per sq ft, set by your school districts[8][10][11] San José says ADUs under 750 sq ft pay none. East Side Union HSD says they do, and most districts only exempt 500 sq ft or less. Ask both of your districts before you budget.
Sewer, storm drain and treatment plant $447 sewer + $270 storm drain per lot; treatment plant $780 per unit[7] The schedule has no ADU-specific line; confirm at the counter whether these apply to your ADU.
Water service Depends on your water company[12][13] San Jose Water, Great Oaks Water, or San José Municipal Water. Separate meters are optional.

The city's own averages by ADU type

ADUTotal
Detached, up to 750 sq ft $13,092
Detached, 751 to 1,200 sq ft $22,312
Attached, up to 750 sq ft $10,729
Attached, 751 to 1,200 sq ft $17,859
Junior ADU $8,137

Averages of ADU permits San José issued in the last 12 months, from the city's Building Fee Estimator. Not a quote. School fees are not included.[1][2]

How we estimate the building cost

The last survey of what Bay Area owners actually paid is from UC Berkeley in 2021: a median of $329 per sq ft for ADUs permitted in 2018 and 2019.[3] Construction prices in California have risen about 60% since then by the state's own cost index (2018-2019 average 6,719 to September 2026: 10,717).[4] We check that against two current numbers and use the spread as the range.

  • UC Berkeley 2021 owner survey, Bay Area median for ADUs built 2018-19 ($329 per sq ft), raised by the California Construction Cost Index (x1.595)[3][4] $525/sq ft
  • San Mateo County ADU Resource Center rule of thumb for design, construction and fees[5] $450 to 600/sq ft
  • Abodu published all-in price, 800 sq ft 2 bed / 2 bath ($424,800)[6] $531/sq ft

Other ADU types

  • Attached ADU: Detached band scaled by the survey's addition-to-detached ratio ($250 vs $300 per sq ft statewide)[3] $375 to 500/sq ft
  • Garage conversion: UC Berkeley 2021 owner survey, statewide median for garage ADUs ($189 per sq ft), raised by the California Construction Cost Index[3][4] $302/sq ft
  • Garage conversion: Same, with the survey's Bay Area premium over the statewide median (x1.32)[3][4] $397/sq ft
  • Garage conversion: SYMBiHOM published garage conversion price, $150K to $225K (per sq ft at a 400 sq ft two-car garage)[14] $375 to 560/sq ft
  • Junior ADU: UC Berkeley 2021 owner survey, statewide median for converting part of the main home ($173 per sq ft), raised by the California Construction Cost Index[3][4] $276/sq ft
  • Junior ADU: Same, with the survey's Bay Area premium (x1.32)[3][4] $363/sq ft

Smaller units cost more per foot. We scale by size the way Abodu's own price list does. The survey counted design and permits in its figure, so a little of the city fee may overlap.

Prefab prices you can check

Abodu published all-in prices (home + typical installation).[6]

  • Studio, 385 sq ft$298,800
  • 1 bed, 500 sq ft$324,800
  • 2 bed / 1 bath, 625 sq ft$358,800
  • 2 bed / 2 bath, 800 sq ft$424,800
  • 3 bed / 2 bath, 1,070 sq ft$464,800
  • 3 bed / 3 bath, 1,195 sq ft$498,800

Not included: Survey package ($6,000), trenching past 50 ft, crane past 100 ft, demolition, site engineering and sales tax.

What other sites say

  • 9Builders: $150,000 to $350,000 in San Jose[15]
  • IMKAT Homes: $205,000 to $415,000 by size[16]
  • ADU Builders Group: $450 to $475 per sq ft[17]
  • SYMBiHOM: $250,000 to $500,000 for a 500 to 1,200 sq ft backyard ADU[14]

None of these pages cites where its number comes from.

Common questions

How much does it cost to build an ADU in San Jose?

For a 750 sq ft detached ADU, our estimate is $350,000 to $465,000 to build, plus about $13,092 in city fees by the city's own numbers. School and utility fees can add more.[1][2][3][4][5]

What are the ADU permit fees in San Jose?

The city's fee estimator averages $13,092 for a detached ADU up to 750 sq ft and $22,312 for 751 to 1,200 sq ft. That covers permit issuance, plan check, trade permits and taxes, not school fees.[1][2]

Do ADUs under 750 sq ft pay impact fees?

No. State law bars impact fees on ADUs under 750 sq ft. Larger ADUs pay in proportion to the main home. School fees follow a different rule, and districts disagree about it, so ask yours.[18]

Is a garage conversion cheaper than a new ADU?

Usually. In the 2021 UC Berkeley survey, garage ADUs had a median cost of $90,000 statewide against $180,000 for detached ones. Raised to 2026 prices, a 400 sq ft garage conversion lands around $120k to $225k by our estimate.[3][4][14]

Sources

Every fact on this page links to one of these. We read each one on the date shown.

  1. 1. City of San José Estimator averages similar permits from last 12 months Checked Oct 18, 2026
  2. 2. City of San José Building Fee Estimator (New ADU results) New ADU estimates: detached 0-750 $13,092 Checked Oct 18, 2026
  3. 3. UC Berkeley Center for Community Innovation Statewide median $150,000/$250sf Checked Oct 18, 2026 read from an archived copy of this official page
  4. 4. California Department of General Services California Construction Cost Index (ENR BCI average of San Francisco and Los Angeles) Checked Oct 18, 2026
  5. 5. San Mateo County ADU Resource Center $450-$600/sf all-in placeholder Checked Oct 18, 2026
  6. 6. Abodu Home From $234,800 Checked Oct 18, 2026
  7. 7. City of San José Building Division ADU 0-750 sf: $454/$1,137/$1,732 Checked Oct 18, 2026 read from an archived copy of this official page
  8. 8. City of San José Fees by ADU size per Building Fee Schedule Checked Oct 18, 2026
  9. 9. City of San José Per-unit ADU parkland fee by MLS zone ($1,700-$8,900) Checked Oct 18, 2026 read from an archived copy of this official page
  10. 10. East Side Union HSD Residential $1.36/sf eff Checked Oct 18, 2026
  11. 11. CA DGS / Office of Public School Construction (State Allocation Board) 2026 maximum Level I residential $5.38/sf (2024: $5.17 Checked Oct 18, 2026
  12. 12. City of San José Water providers: San Jose Water, Great Oaks Water, San José Municipal Water System Checked Oct 18, 2026 read from an archived copy of this official page
  13. 13. City of San José First building review typically 20 business days Checked Oct 18, 2026
  14. 14. SYMBiHOM Garage conversion $150K-$225K Checked Oct 18, 2026
  15. 15. 9Builders FAQ: SJ ADU $150k-$350k, rents $1,800-$3,000/mo, unsourced Checked Oct 18, 2026
  16. 16. IMKAT Size-tier cost table $205k-$415k, unsourced Checked Oct 18, 2026
  17. 17. ADU Builders Group $450-$475/sq ft Checked Oct 18, 2026
  18. 18. California Department of Housing and Community Development (HCD) All state ADU/JADU rules used in state_baseline.md (sizes, heights, setbacks, parking, owner-occupancy, JADU, Checked Oct 18, 2026