Acton ADU
Based in Campbell, Santa Clara County
CSLB #638333 active Class B Licensed 34 years
- Detached
- Ready-made plans
- Lists Burlingame on its own site
- No public complaints on its CSLB record
- Publishes general price ranges
Two numbers, kept apart. City fees come from the city's own fee pages. The build price is our estimate from the last owner survey and today's published prices. How we got it
Official City fees
Line by line
The city doesn't publish a total for an ADU, so we list each charge.See every fee [1]
All in, before school and utility fees: about $350k to $465k for a 750 sq ft detached ADU. Adjust it for your lot
7 licensed builders list Burlingame on their own sites. Your quote request goes to the Bay Area ADU Builders team.
Get 3 quotes7 licensed builders list Burlingame on their own sites. Three quotes for your lot show where in the range you land. Your request goes to the Bay Area ADU Builders team.
Get 3 quotesChange the type and size. City fees come from Burlingame's own averages; the building cost is our estimate.
Building (middle) City fees School fees Parkland
Not included: water and sewer connection, and site surprises like a long utility run or a crane. See the fee list below.
Get 3 quotes to check this numberThe top three by our public score for Burlingame. Some publish prices, which is the quickest check on the estimate above.
Based in Campbell, Santa Clara County
CSLB #638333 active Class B Licensed 34 years
Based in Mill Valley, Marin County
CSLB #1117837 active Class B Licensed 2 years
Based in Redwood City, San Mateo County
CSLB #1102654 active Class B Licensed 3 years
| Building permit (valuation-based) | ICC valuation x 2.29, then a tiered fee table[1] For example, a $100,001 to $500,000 valuation pays $5,218.30 plus $9.15 per extra $1,000. |
|---|---|
| Plan review and surcharges | Building plan review 65% of the permit fee; planning and engineering review 25% each where they apply; technology fee 2%; general plan maintenance 0.2% of valuation[1] Plan check fees are due when you submit. |
| Development impact fees | $9,391 per single-family unit[1][6] General $2,825, library $2,443, police $448, parks $605, traffic $1,612, fire $658, storm drain $801. The schedule has no ADU line; state law bars impact fees under 750 sq ft. |
| School fees | San Mateo Union HSD $2.15 per sq ft, plus Burlingame School District[7][8][6] Burlingame SD's 2024 study proposed $3.10 per sq ft; we could not confirm the adopted rate. Under state law, ADUs of 500 sq ft or less pay no school fees. |
| Sewer capacity charge (City of Burlingame) | $5 per sq ft for ADUs over 150 sq ft[1] |
| Water capacity charge (City of Burlingame) | $3 per sq ft for ADUs over 150 sq ft[1] A water service connection with sidewalk replacement is $995. |
The last survey of what Bay Area owners actually paid is from UC Berkeley in 2021: a median of $329 per sq ft for ADUs permitted in 2018 and 2019.[2] Construction prices in California have risen about 60% since then by the state's own cost index (2018-2019 average 6,719 to September 2026: 10,717).[3] We check that against two current numbers and use the spread as the range.
Smaller units cost more per foot. We scale by size the way Abodu's own price list does. The survey counted design and permits in its figure, so a little of the city fee may overlap.
Abodu published all-in prices (home + typical installation).[5]
Not included: Survey package ($6,000), trenching past 50 ft, crane past 100 ft, demolition, site engineering and sales tax.
None of these pages cites where its number comes from.
For a 750 sq ft detached ADU, our estimate is $350,000 to $465,000 to build. School and utility fees can add more.[1][2][3][4]
The city doesn't publish a total. No published total; see fee lines The fee lines on this page list each charge.[1]
No. State law bars impact fees on ADUs under 750 sq ft. Larger ADUs pay in proportion to the main home. School fees follow a different rule, and districts disagree about it, so ask yours.[6]
Every fact on this page links to one of these. We read each one on the date shown.